The short answer: “semi-finished” (نصف تشطيب) is not a standard specification; what binds the seller is what your contract and its specification annex say. Check the items below and write down your notes before you sign for the unit.
What does “semi-finished” usually mean?
In Egypt it usually means the unit is handed over with electrical and plumbing rough-in, door frames and plaster, and sometimes windows and other works. What it includes varies by developer and by contract, so the only reference is the contract and its specification annex, not the market name.
Documents to ask for before the inspection
- The contract and the specification annex.
- The unit’s architectural drawings if available, and the electrical and plumbing drawings.
- Anything about meters and utilities, and the status of their connection.
The checklist
Print this list, use it during the inspection and write your notes in the last column:
| Item | What to check | Your notes |
|---|---|---|
| Plaster | Level and plumb with a straightedge, corners, cracks, and hollow areas by tapping | |
| Electrical rough-in | Box positions against the plan, the board, the earthing route | |
| Plumbing rough-in | Supply and drain pipes, falls, and a pressure test if possible | |
| Openings and frames | Sizes, plumb and the condition of the door frames | |
| Ceilings | Cracks and signs of damp or leaks | |
| Floors | Levels, and any large differences between rooms | |
| Windows, if fitted | Sealing, glass and smooth opening and closing | |
| Roof and facade | Signs of water leaks, especially on the top floor | |
| Meters and utilities | Present, or connection status as in the contract |
How to write the defects record
- For each item, note where it is (room and wall) and what it is, with a photo.
- Number the items so their repair is easy to track.
- Ask the seller to sign the record or answer it in writing.
- Do not sign final handover before the important items are closed.
If the seller refuses to fix things
Go back to the contract terms on handover and defects, and keep the record, photos and messages. For legal disputes, consult a lawyer before you sign.
When to call an engineer
Some defects are hard to spot without training, such as hollow plaster or wrong drain falls. See the handover inspection service. After handover, read apartment finishing stages, in order and how to work out finishing costs.
General information for planning; it does not replace an engineer’s on-site assessment of your case.