Costs and budgeting

What it costs to finish a 100 m² apartment: a line-by-line method

Last updated:

The short answer: there is no single correct price per square metre for finishing. The real cost of your unit is the sum of the BOQ items, each quantity multiplied by its rate, plus a contingency for the unexpected. This guide works through the calculation step by step for a 100 m² apartment.

Why do per-m² prices vary so much?

A “price per metre” for finishing is a bundled figure that hides many assumptions, so it changes from one quote to the next. Among the reasons:

  • The unit’s state: a bare-brick flat needs every item, a semi-finished one needs part of them, and an older flat needs demolition before anything else.
  • The level: local ceramic versus imported porcelain, or simple emulsion versus special paints, makes a big difference.
  • Bathrooms and kitchen: the most expensive parts of a flat, because they combine plumbing, waterproofing, tiles and fittings.
  • Ceilings: plaster and paint only, or gypsum board with hidden lighting.
  • Electrics and air conditioning: the number of points, and AC piping to every room or only some.
  • Doors and windows: the type of timber, the aluminium profile and the glass.
  • Floor level and access: carrying materials to a high floor without a lift adds cost.
  • What the quote includes: some quotes include sanitary ware and the kitchen, others do not.

So do not compare one “price per metre” with another; compare the same items at the same specifications.

Step 1: Establish the unit’s state

StateWhat it usually needs
Bare brick (shell)Every item: services, waterproofing, plaster, ceilings, floors, paint, doors and windows, and fittings.
Semi-finishedWhat it means varies by developer; services, plaster and door frames are often done, and the rest remains. Check your contract first.
Finished but needs renovatingRemoving what will be renewed, checking the services, then only the items needed.

If your unit is semi-finished, read taking over a semi-finished apartment to see what should already be done before you start.

Step 2: List the items

List every item you will need, grouped by trade: electrics, plumbing, waterproofing, plaster, gypsum board, floors, wall tiles, paint, joinery, aluminium, sanitary ware, kitchen, air conditioning and cleaning. Give each item a unit (m², linear metre, number or lump sum) and a clear specification. Start from the apartment finishing BOQ template.

Step 3: Work out the quantities

This is a hypothetical example of a 100 m² apartment with about 85 m² of net floor area, two bathrooms and a kitchen. The quantities are rough and only illustrate the method; they are not your unit’s:

ItemQuantity in the exampleHow it was worked out
Floor tiles85 m², about 94 m² with 10% wasteNet floor area
Wall tiles, two bathroomsAbout 35 m²Each bathroom: 8 m perimeter × 2.4 m height, minus the door
Kitchen wall tilesAbout 6 m²Worktop length × tiled height above it
Wall plaster and paintAbout 300 m²Sum of room perimeters × height, minus openings
Ceiling paintAbout 85 m²Roughly equal to the floor area
Internal doors6 doorsCounted from the plan
WindowsBy the size of each openingEach opening measured separately

For tiles and paint, use the tile calculator and the paint calculator.

Step 4: Get item prices from three quotes

Send the same BOQ, with the same specifications, to at least three contractors or suppliers, and ask for a price for every item. Put the prices side by side in a table. Any item whose price varies a lot between quotes deserves a question: did everyone read the specification the same way?

Step 5: Add a contingency and list the exclusions

Add about 10% of the total for the unexpected, and possibly more in older units. Write down clearly what the calculation leaves out, such as furniture, appliances, air-conditioning units, and utility fees and meters.

Mistakes that push the budget over the estimate

  • Relying on a verbal price per metre with no written items.
  • Items written in vague terms, such as “as per good practice”, with no specification.
  • Changing decisions during the work without working out the effect on cost and schedule.
  • Forgetting small items that add up: accessories, switches and sockets, cleaning and debris removal.
  • Leaving no contingency.

When to call an engineer

If you have no drawings, or the quotes you received are very different and you cannot see why, a BOQ prepared by an engineer saves a lot. See BOQs and quantity take-off, compare the finishing levels, or request a quote for your unit.

General information for planning; it does not replace an engineer’s on-site assessment of your case.