The short answer: a BOQ (bill of quantities, مقايسة) is a table that lists every finishing item with its unit, quantity, specification and rate. When every contractor prices the same BOQ, you can compare quotes item by item instead of comparing totals you cannot see inside.
How to read a BOQ
- Item number: to order the items and refer to them in the contract and in messages.
- Description and specification: what will be done, with which material, grade and size.
- Unit: m², linear metre, number or lump sum.
- Quantity: from site measurements or the drawings.
- Rate and total: filled in by the contractor; total = quantity × rate.
The BOQ template
The rate and total columns are left blank for each contractor to fill in. Adjust the items, quantities and specifications to your unit, and print the page with the print button.
| No. | Item and specification | Unit | Quantity | Rate | Total |
|---|---|---|---|---|---|
| 1 | Preparation: removing existing finishes and taking debris off site | Lump sum | |||
| 2 | Electrics: lighting point with conduit, box and cable, to the layout drawing | No. | |||
| 3 | Electrics: socket point | No. | |||
| 4 | Electrics: air-conditioning point on its own circuit | No. | |||
| 5 | Electrics: distribution board with breakers sized from the load calculation | No. | |||
| 6 | Electrics: supply and fit switches, sockets and light fittings (state the range) | No. | |||
| 7 | Plumbing: full bathroom rough-in (supply and drainage) with a pressure test | No. | |||
| 8 | Plumbing: kitchen rough-in (supply and drainage) | No. | |||
| 9 | Waterproofing: bathroom floor, turned up the walls, with a flood test | m² | |||
| 10 | Waterproofing: kitchen floor, where the design calls for it, with a flood test | m² | |||
| 11 | Plaster: walls and ceilings, set out with dots and screeds | m² | |||
| 12 | Gypsum board: suspended ceiling on a metal frame, to the design | m² | |||
| 13 | Floors: supply and lay porcelain or ceramic (state size and grade), with skirting | m² | |||
| 14 | Wall tiles in bathrooms and kitchen (state size and grade) | m² | |||
| 15 | Paint: sealer, putty and coats of paint (state number and type) | m² | |||
| 16 | Joinery: internal door with frame and ironmongery (state type) | No. | |||
| 17 | Aluminium: windows (state profile and glass) | m² | |||
| 18 | Sanitary ware: supply and fit (state items and range) | No. | |||
| 19 | Kitchen: units and worktop to the design | Linear metre | |||
| 20 | Air conditioning: copper and drain piping for each unit | No. | |||
| 21 | Final cleaning and handover | Lump sum |
How to compare three quotes
- Send the same BOQ, with the same quantities and specifications, to every contractor.
- Put the prices side by side, item by item, in one table.
- Ask about items whose price varies a lot between quotes.
- Make sure every quote kept to the written specification and did not change it.
- Compare totals at the end, not at the start.
Common BOQ mistakes
- Items in vague terms, such as “as per good practice”, with no specification.
- Lump sums for everything, so you cannot see what you are paying for.
- No clear list of what the quote leaves out.
- Guessed quantities with no measurement.
When to call an engineer
An accurate BOQ needs measuring and knowledge of the items and their specifications. See BOQs and quantity take-off, work out some quantities yourself with the tile calculator and the paint calculator, and read how to work out finishing costs.