Templates and checklists

Apartment finishing BOQ template (printable)

Last updated:

The short answer: a BOQ (bill of quantities, مقايسة) is a table that lists every finishing item with its unit, quantity, specification and rate. When every contractor prices the same BOQ, you can compare quotes item by item instead of comparing totals you cannot see inside.

How to read a BOQ

  • Item number: to order the items and refer to them in the contract and in messages.
  • Description and specification: what will be done, with which material, grade and size.
  • Unit: m², linear metre, number or lump sum.
  • Quantity: from site measurements or the drawings.
  • Rate and total: filled in by the contractor; total = quantity × rate.

The BOQ template

The rate and total columns are left blank for each contractor to fill in. Adjust the items, quantities and specifications to your unit, and print the page with the print button.

No.Item and specificationUnitQuantityRateTotal
1Preparation: removing existing finishes and taking debris off siteLump sum
2Electrics: lighting point with conduit, box and cable, to the layout drawingNo.
3Electrics: socket pointNo.
4Electrics: air-conditioning point on its own circuitNo.
5Electrics: distribution board with breakers sized from the load calculationNo.
6Electrics: supply and fit switches, sockets and light fittings (state the range)No.
7Plumbing: full bathroom rough-in (supply and drainage) with a pressure testNo.
8Plumbing: kitchen rough-in (supply and drainage)No.
9Waterproofing: bathroom floor, turned up the walls, with a flood testm²
10Waterproofing: kitchen floor, where the design calls for it, with a flood testm²
11Plaster: walls and ceilings, set out with dots and screedsm²
12Gypsum board: suspended ceiling on a metal frame, to the designm²
13Floors: supply and lay porcelain or ceramic (state size and grade), with skirtingm²
14Wall tiles in bathrooms and kitchen (state size and grade)m²
15Paint: sealer, putty and coats of paint (state number and type)m²
16Joinery: internal door with frame and ironmongery (state type)No.
17Aluminium: windows (state profile and glass)m²
18Sanitary ware: supply and fit (state items and range)No.
19Kitchen: units and worktop to the designLinear metre
20Air conditioning: copper and drain piping for each unitNo.
21Final cleaning and handoverLump sum

How to compare three quotes

  1. Send the same BOQ, with the same quantities and specifications, to every contractor.
  2. Put the prices side by side, item by item, in one table.
  3. Ask about items whose price varies a lot between quotes.
  4. Make sure every quote kept to the written specification and did not change it.
  5. Compare totals at the end, not at the start.

Common BOQ mistakes

  • Items in vague terms, such as “as per good practice”, with no specification.
  • Lump sums for everything, so you cannot see what you are paying for.
  • No clear list of what the quote leaves out.
  • Guessed quantities with no measurement.

When to call an engineer

An accurate BOQ needs measuring and knowledge of the items and their specifications. See BOQs and quantity take-off, work out some quantities yourself with the tile calculator and the paint calculator, and read how to work out finishing costs.

General information for planning; it does not replace an engineer’s on-site assessment of your case.

Want an engineer to look at your case?

Send your unit’s details and photos in two minutes, or message us on WhatsApp.

WhatsApp (opens WhatsApp)