A concrete calculator for slabs, footings, columns and beams: enter each element’s dimensions and number, or the volume directly, to get the concrete volume, cement bags, sand and gravel for the mix.
Assumptions (you can change them)
The result updates as you type.
Result
Complete the fields to see the result
- Concrete volume
- — m³
- Cement bags
- —
- Sand
- — m³
- Gravel
- — m³
- Volume with waste
- — m³
- Cement
- — kg
- Cement in tonnes
- — t
Estimates for planning; final quantities after a site visit or a design.
- The real mix comes from the structural drawings and trial mixes (Egyptian code ECP 203).
Your list is long: only the totals and settings are attached to the request. You can send the full list on WhatsApp.
Send the result on WhatsApp (opens WhatsApp)How it is calculated
Each element’s volume is its dimensions multiplied together and by its number: a slab is length × width × thickness, a footing length × width × depth × number, a column its two sides × height × number, a beam width × depth × length × number. The volumes are added up and the waste is added, then cement in kilograms from the cement content per m³, and sand and gravel at their ratios per m³.
Vw = ΣV × (1 + waste/100) · bags = ⌈Vw × c ÷ 50⌉ · sand = 0.4 × Vw · gravel = 0.8 × Vw
This is a common nominal mix, for planning only. The real mix comes from the structural drawings and trial mixes under the Egyptian code (ECP 203).
Assumptions
| Assumption | Default | Note |
|---|---|---|
| Default element | Slab 5 × 4 m, 0.15 m thick | Add footings, columns, beams or a direct volume |
| Cement per m³ | 350 kg | Choices: 250 (plain blinding), 300, 350, 400 |
| Sand | 0.4 m³ per m³ | |
| Gravel | 0.8 m³ per m³ | |
| Waste | 5% | |
| Bag | 50 kg |
Every value can be changed in the calculator.
Worked example
A 5 × 4 m slab, 0.15 m thick, with 350 kg of cement per m³ and 5% waste:
- Concrete volume = 5 × 4 × 0.15 = 3.00 m³
- With waste = 3 × 1.05 = 3.15 m³
- Cement = 3.15 × 350 = 1102.5 kg, that is 23 bags of 50 kg
- Sand = 3.15 × 0.4 = 1.26 m³
- Gravel = 3.15 × 0.8 = 2.52 m³
Measuring tips
- Take slab thickness and element sizes from the structural drawings.
- Use the clear height of columns between slabs.
- Do not count the zone where a beam meets the slab twice.
- When ordering ready-mix, add a small margin for losses.
Estimates for planning; final quantities after a site visit or a design.
Common questions
How many bags of cement per cubic metre of concrete?
With 350 kg of cement per m³: seven 50 kg bags per m³ before waste. The design sets the real mix.
What is the difference between blinding and reinforced concrete?
Blinding is a plain layer without steel under the footings, with less cement (250 kg per m³ in the calculator). Reinforced concrete contains rebar, and its mix is designed to carry loads.
Why does the mix differ between projects?
Because the required strength, aggregate size, cement type and casting conditions differ. The structural drawings and trial mixes set the real mix; the figures here are for planning only.
