Apartment finishing contract: clauses to check before you sign

Last updated:

The short answer: before you sign a finishing contract, make sure it sets out the scope with an attached BOQ, the specifications, the schedule, payments tied to completed and checked stages, how changes are handled, handover, and who puts defects right. This guide is general information, not legal advice; have a lawyer read the contract before you sign.

Types of finishing contract

TypeHow it worksSuits you whenWatch out for
Lump sumOne price for all the workThe scope and specifications are clear and written in detailAny vague specification tends to be read in favour of the cheaper material
Re-measured (by item)A rate per unit; quantities are measured as the work is doneFinal quantities are uncertainThe measurement method must be written into the contract
Cost-plusYou pay the actual cost against invoices, plus an agreed percentageYou want full transparency on materialsIt needs close checking of invoices and quantities
Management feeYou contract the trades directly and an engineer manages the work for a feeYou want control over buying and the tradesResponsibilities must be written down clearly

Clauses to check before you sign

ClauseWhat it should say
PartiesNames and roles, who signs and who represents each side
ScopeThe BOQ, specifications and drawings attached as annexes
Samples and approvalsHow materials are approved before they are bought
ScheduleStart date, the duration of each stage and the handover date
PaymentsTied to completed, checked stages, with an amount held back until final handover (5–10% is common)
ChangesWritten down, priced and scheduled before they are carried out
DelaysAccepted causes of delay, and what follows an unjustified delay
TestsPipe pressure tests and waterproofing flood tests before anything is covered
HandoverProvisional handover with a snag list, then final handover once it is fixed
Defects after handoverWritten periods for putting defects right, for each type of work
SafetyResponsibility for the site and the safety of workers and neighbours
TerminationWhen each side may end the contract, and how completed work is valued
DisputesHow disagreements are settled

The legal frame in brief

  • Article 651 of the Egyptian Civil Code makes the architect and the contractor jointly liable, for ten years, for total or partial collapse of what they built and for defects that threaten the building’s strength and safety.
  • Any clause that removes or limits this liability is void (Article 653), and a claim must be brought within three years of the collapse or the discovery of the defect (Article 654).
  • For some contracting work, the law requires a contractor registered with the Egyptian Federation for Construction and Building Contractors; check the registration of whoever you contract with when the law requires it.
  • Structural work, facade changes and extra floors need a permit under Article 39 of Building Law 119 of 2008.

When to call an engineer

An engineer who checks the technical side of the contract (the BOQ, specifications, payments and handover) before you sign protects you from expensive gaps. Ask for an engineering consultation to check the contract before signing, and read the BOQ template and how we work. To work out some quantities, use the tile calculator.

Sources

  • Egyptian Civil Code (Law 131 of 1948), Articles 651, 653 and 654.
  • Building Law 119 of 2008, Article 39.

Last checked: 7 November 2026.

General information for planning; it does not replace an engineer’s on-site assessment of your case.