Finishing step by step

Apartment finishing stages, in the right order

Last updated:

The short answer: this is the usual order for finishing an apartment:

  1. Survey, design and BOQ.
  2. Demolition and any non-structural changes.
  3. Electrical, plumbing, drainage and air-conditioning rough-in.
  4. Bathroom and kitchen waterproofing, with a flood test.
  5. Door frames and window openings.
  6. Plaster.
  7. Gypsum board and ceilings.
  8. Floors and wall tiles.
  9. Putty and the first coats of paint.
  10. Aluminium, doors and kitchen.
  11. Electrical fittings and sanitary ware.
  12. The final coat of paint and cleaning.
  13. Handover and the snag list.

Every stage has a hold point: do not move on until you are sure that what is about to be covered is sound.

1. Before you start: survey, design and BOQ

Measure the unit, decide where furniture and appliances go, and write the items and specifications into a BOQ. Hold point: an agreed layout of electrical and plumbing points before anything is broken out. Common mistake: starting before the kitchen, bathrooms and air conditioning are placed.

2. Demolition and changes

Removing old tiles or non-load-bearing walls where needed. Hold point: confirming that a wall to be removed is not load-bearing and does not carry a beam or column. Common mistake: cutting a structural element to widen an opening without a design and a permit.

3. Electrical, plumbing and air-conditioning rough-in

Electrical conduits and boxes, supply and drain pipes, and AC piping. Hold point: a pressure test of supply pipes, a check of drain falls, and photos of the routes. Common mistake: plastering over the routes without a test or photos.

4. Waterproofing and the flood test

Waterproofing bathroom and kitchen floors and turning it up the walls. Hold point: flooding the area for the period the system requires and watching for leaks before tiling. Common mistake: tiling straight after waterproofing with no test.

5. Door frames and window openings

Fixing the door frames and setting the window openings before plastering. Hold point: plumb, alignment and the finished floor level. Common mistake: fixing a frame without allowing for the finished floor thickness, leaving a gap under the door.

6. Plaster

It starts with level dots and screeds (setting-out guides), then the plaster coats. Hold point: level, plumb and corners checked with a straightedge and spirit level. Common mistake: plastering without screeds, so the walls look uneven under paint.

7. Gypsum board and ceilings

Suspended ceilings and hidden lighting to the design. Hold point: a level frame, and the positions of lighting and AC openings before it is closed. On the order: gypsum is usually done before the floors so scaffolding and dust do not damage them, though this can change with the floor type.

8. Floors and wall tiles

Hold point: level, hollow tiles (found by tapping), straight joints and falls to the drains in wet areas. Common mistake: buying tiles from different production batches, so the colour does not match.

9. Putty and the first coats of paint

Sealer, then putty, then sanding, then the first coats. Hold point: a smooth, even surface under side lighting before painting. Common mistake: painting plaster that has not dried.

10. Aluminium, doors and kitchen

Fitting windows, doors and kitchen units once the dusty work is over. Hold point: sealing and smooth opening and closing. On the order: aluminium is sometimes fitted before the final paint to keep dust and rain out, with a protective cover.

11. Electrical fittings and sanitary ware

Switches, sockets and lights, then sanitary ware and mixers. Hold point: testing every point, and no leaks under basins or behind fittings.

12. Final coat and cleaning

The last coat goes on at the end so fitting work does not mark the walls, followed by a full clean.

13. Handover and the snag list

Inspect every room, write a snag list with photos, and do not sign final handover until the items are fixed. For a final check before you sign, an engineer can inspect the unit with you: see handover inspection.

The hold points at a glance

StageHold pointEvidence
Electrical rough-inRoutes, box positions and circuit continuityPhotos of the routes and the test result
Plumbing and drainageSupply pressure test and drain fallsTest result and photos
WaterproofingFlood test before tilingPhotos at the start and end of the test
PlasterLevel, plumb and cornersStraightedge and spirit-level measurements
CeilingsLevel frame and opening positionsPhotos before closing
FloorsLevel, hollow tiles and fallsTapping the tiles and measuring the level
PaintSurface preparation and number of coatsVisual check under suitable light
FittingsWorking, with no leaksA test run and a snag list

When to call an engineer

An engineer who checks each hold point at the right time prevents mistakes that are hard to fix once covered. Read about apartment finishing led by a civil engineer and how we work, and work out your quantities with the tile calculator and the paint calculator.

General information for planning; it does not replace an engineer’s on-site assessment of your case.

Want an engineer to look at your case?

Send your unit’s details and photos in two minutes, or message us on WhatsApp.

WhatsApp (opens WhatsApp)